Building your own house is a dream that can become a nightmare or one of the finest things you do in your life. I have seen both. What separates the two stories is not the budget, it is the order in which things are done and the people you trust. Here is the route as I recommend it.
First of all: are you sure you want to build?
Building takes time (often more than planned), presence (or a trusted person on site), a budget with a margin, and tolerance for stress. If you are not on site, or if you lack time, buying an existing villa or a turnkey new build may be safer. See buying a villa and developers in Agadir.
Step 1: choosing and securing the land
This is the most important decision. Check:
- The land title: is the plot registered? Who is the owner? Are there encumbrances? See land title.
- The planning status: is the plot buildable? In which zone? What rules (height, footprint, setback)? Ask the planning services.
- Easements: right of way, networks, alignments, public projects (roads, tramway, etc.).
- Servicing: road access, water, electricity, drainage.
- The nature of the soil: a geotechnical study is strongly recommended, since Agadir is in a seismic zone and building rules are strict.
- The boundaries: boundary marking, neighbours, walls.
- Debts: unpaid taxes, disputes.
"Cheap" land without a title or in a non-buildable zone is trap number one. Agricultural or unsubdivided land may look like a good deal, but does not allow legal building, and can cost you dearly in demolition or litigation.
Step 2: the architect
For a building project, the architect is generally mandatory for filing the permit and for the design. A good architect:
- Knows the local planning rules and the earthquake-resistance standards.
- Understands your way of life and your budget.
- Knows how to design for the climate: orientation, ventilation, shading, terraces.
- Can follow the site and supervise the contractors.
Ask for references, visit completed work, meet several. The contract must specify: assignment (design only, permit, site supervision), fees, schedule. Fees are generally expressed as a percentage of the cost of works, but this is negotiable and depends on the assignment.
Step 3: the building permit
The permit file is submitted via the architect to the competent services. It generally includes: plans, title deed, calculation notes, administrative documents. Processing can take several weeks to several months. Never start the site without a permit. Building without authorisation can lead to a stop-work order, fines, even demolition.
Step 4: the budget
The cost of construction depends on the finish level, the surface area, the plot, the soil, the foundations, the materials. Prices change with materials and labour. I do not give you a per-square-metre figure, as it would quickly be wrong: ask several firms for detailed quotes and compare like for like.
Plan for:
- Land + acquisition costs
- Architect and engineering consultants
- Structural work (foundations, structure, walls)
- Finishing trades (plumbing, electrics, plastering, flooring)
- Finishes (paint, joinery, kitchen, bathrooms)
- Outdoor works (fence, pool, garden)
- Connections (water, electricity, drainage)
- Insurance
- A 10 to 20% margin for the unexpected and overruns
A construction budget without a margin is an unrealistic budget. I know of no site that did not have at least one surprise.
Step 5: the contractors and the site
Three ways to proceed:
- General contractor: a single contact for everything. Simpler, sometimes dearer.
- Separate trades: you (or the architect) coordinate mason, plumber, electrician, etc. Potentially cheaper, but more management.
- Developer or builder: turnkey, but to be framed by a precise contract.
Whichever you choose:
- Demand written quotes, detailed, dated, signed.
- Make a contract: price, deadline, late penalties, guarantees, payment terms.
- Pay in stages tied to progress, no excessive advance.
- Keep the invoices and proof of payment.
- Have the site supervised by the architect or a trusted technician.
- Visit often: an unsupervised site drifts.
Step 6: handover and compliance
At the end of the works: handover with a snagging list, correction of defects, then obtaining the occupancy permit or compliance certificate, necessary for final connections, insurance and resale. Do not move in permanently without it.
The classic pitfalls
- Land without a title or non-buildable.
- Unqualified architect or one never on site.
- A contractor who disappears after the deposit.
- Incomplete quotes that balloon along the way.
- Underestimating the timetable: a house build often lasts much longer than announced.
- Building outside the permit: extensions, unauthorised floors.
- Earthquake standards ignored: Agadir remembers the 1960 earthquake. See history of Agadir.
- No supervision if you live abroad.
Building to let?
If your idea is to build to let (for instance seasonally), check the regulations and the real profitability. See seasonal letting and yield and risks.
My view as a resident
If you have never built, start with a simple project: simple shapes, common materials, no pool or complications in the first year. Surround yourself with a serious architect, an attentive notary and firms recommended by people who have built recently. And above all, do not rush.
To complete: notary and lawyer · acquisition costs · can a foreigner buy?.
Planning rules, building standards and permit procedures change and depend on each plot. Have your project checked by a licensed architect and a notary before any commitment.